NEW INFORMATION – FRIDAY 5th MARCH 2010

NEW INFORMATION – FRIDAY 5th MARCH 2010

See more.

WE ARE PLEASED TO ADVISE OUR E-MAIL SERVICE IS ON LINE AS FROM TUESDAY MORNING.

IN SAN ANTONIO AND TALCAHUANO OFFICES E-MAIL IS NOT ACTIVE THEREFORE ALWAYS PLEASE CHANNEL THROUGH OUR MAIN OFFICE.

TELEPHONE SERVICE IS OPERATIONAL EXCEPT FOR OUR SAN ANTONIO BRANCH OFFICE WHICH IS OPERATING WITH MOBILE PHONES AND TALCAHUANO AND CORONEL WHERE NO PORTS WORKING AND OFFICE TEMPORARILY CLOSED.

THE SITUATION OF PORTS IN CHILE IS THE FOLLOWING:

ARICA

NO DAMAGES WORKING

IQUIQUE

NO DAMAGES WORKING

MEJILLONES

NO DAMAGES WORKING

ANTOFAGASTA

NO DAMAGES WORKING

COQUIMBO

NO DAMAGES - WORKING

VENTANAS  LNG TERMINAL

WORKING

VENTANAS MULTICRUDE BUOY

OPERATIONAL

VENTANAS SBM

NOT OPERATIONAL

PUERTO VENTANAS BULK TERMINAL

BERTHS 1 AND 3 OPERATIONAL.

BERTH 2 REPAIRS START TODAY, EXPECT FINISHED MARCH 8-9

BERTH 5 NOT OPERATIONAL, NO DATE FOR REPAIRS COMPLETION

VENTANAS OXIQUIM TERMINAL

NOT OPERATIONAL

VALPARAISO TPS BERTHS 1, 2 AND 3

WORKING

VALPARAISO TPS BERTHS 4 AND 5

UNDER EVALUATION NOT WORKING

VALPARAISO EPV BERTH 6

WORKING ONLY LIGHT CARGO (MAINLY FRUIT)

VALPARAISO EPV BERTH 7

DAMAGED, NOT WORKING

VALPARAISO EPV BERTH 8

WORKING ONLY LIGHT CARGO (MAINLY FRUIT)

SAN ANTONIO STI BERTHS 1  AND 3

WORKING.

SAN ANTONIO STI BERTH 2

NOT OPERATIONAL

SAN ANTONIO EPSA BERTH 4 AND 5

WORKING, RESTRICTED TO ONE VESSEL ONLY

SAN ANTONIO EPSA BERTHS 6 AND 7

NOT WORKING

SAN ANTONIO PANUL GRAIN BERTH

NOT WORKING

CONCEPCION BAY AND SURROUNDING PORTS

CLOSED FOR EVALUATION. NO PORTS WORKING. LIRQUEN AUTHORISED TO WORK BUT SEVERE RESTRICTIONS ON AVAILABILITY OF TUGS, LAUNCHES AND PILOT SERVICE. FURTHERMORE, EXTENSIVE CURFEW PLACES RESTRICTIONS ON AVAILABILITY OF LABOUR.